Case Study: Dewsbury

November 28, 2024

Services: Gas Infrastructure

Client: J.P. Wild

Location: Churwell Vale, Dewsbury

This project required a new 90mm gas service to be installed to an existing warehouse. The necessary permit was obtained from the local council, and approval was secured from Northern Gas Networks (NGN) to proceed with the project.


During the planning phase, there was some confusion regarding the size of the parent main, which required clarification with NGN to ensure proper compliance and alignment with specifications.


Once this issue was resolved, the installation process was carried out smoothly, and the job was completed efficiently. Take a look through some of the project images below.