Giles Lane Block E
December 18, 2025
Services: New Electric Service
Client: WW Martin
Location: Canterbury
Argon installed a 300 mm 3-core waveform cable from the Point of Connection (POC) to the internal termination point, a 600 amp HDCO located in the plant room. The project was for a university accommodation development in the heart of Canterbury.
The council initially requested a full road closure; however, following on-site meetings with the council, the works were successfully completed under traffic light control, minimising disruption to local residents. UKPN carried out the energisation, and UKPD acted as the adopting IDNO.